Utilities (storm, water & sewer) are 95% complete at the job site. Original rock retaining walls and Curb & Gutter on parking lot islands are 100% complete. Overall grading is 95% complete, only pending select fill in shops and on fire lanes. All site work, including paving and striping, anticipated being completed by the beginning of August.
ZTEX Construction is currently working at the Walmart at West Towne Marketplace. The project began Monday 04/17/17 and over-excavation completed on 04/24/17. Select fill material placement completed in 16 working days. Currently working on the fine grade pads and will have the pad elevations certified by Professional Surveyor.